2022 Street Overlay Project to Begin Thursday, October 20th.

Posted on Tuesday October 18, 2022
 
The City of Pleasant Hill 2022 Street Overlay Project will begin Thursday, October 20th lasting approximately 1 week, weather permitting. Here are the streets scheduled for overlay:
*Crest Drive
*Delaware - 7 Hwy to Madison St.
*Campbell St - Myrtle St. to Timber St.
*Industrial Dr. - 7 Hwy to 1010 Timber
*Sugarland Parkway
*Mulberry St. - Mulberry Ct. to near Redwood Cir.
The plan is to mill and patch Delaware St, Crest Dr, and Campbell St on Thursday. They will move to Sugarland Pkwy and Industrial Dr on Friday and Mulberry St on Saturday. Paving will begin on Monday and follow the same route. The schedule will greatly depend on the amount of patching and of course the weather. We will continue to update if there are any changes.