2024 Street Overlay Program
Who’s Responsible: Tony Bakken | Email: [email protected] | Phone: (816) 540-9130
Contractor: Superior Bowen
Budget: $873,492.50
Funding Source: Transportation Fund
Locations:
- Lexington Road from 163rd Street to State Route VV
- Russell Road from Lexington Road to Wright Street
- Matthes Lane from 7 Highway to Russell Road
- Wright Street from 7 Highway to end
- Hillcrest Street from Maple Lane to Country Club Drive
TIMELINE:
- COMPLETED: Summer 2024 - Contract
- Construction
- Completion
DESCRIPTION:
The Street Maintenance Program is designed to increase the longevity of the roadways around the City. One of the methods utilized is street overlay. The process involves milling the existing roadway a number of inches (typically 2 to 4 inches), completing some base repairs, and then applying a new layer of asphalt over an existing road surface to repair and extend its lifespan.
CURRENT STATUS:
08/12/2024 - Contract approved