7 Highway Water Line Replacement
From Matthes Lane to Timber Street along MO-7 Highway
Who’s Responsible: Tony Bakken | Email: [email protected] | Phone: (816) 540-9130
Budget: $1,000,000
Funding Source: Series 2023 Water/Sewer Revenue Bond
Location: MO-7 Highway from Matthes Lane to Timber Street
TIMELINE:
- COMPLETED: Winter 2024 - Planning and Design
- COMPLETED: Summer 2024 - Permitting Plan Reviews, Easements, and Bidding
- Fall 2024 - Construction
- Spring 2025 - Completion
PROJECT DESCRIPTION:
The 7 Highway Water Line Replacement Project will replace a water line that has seen a series of leaks and breaks over several years, particularly north of Renee Lynde Drive. The goal of construction will be to replace the existing deteriorating water line, which significantly reduces the chances of a water line break and helps eliminate unexpected water disruptions to customers in the surrounding area. In addition to the water main replacement, the plans call for a water main extension to serve as a secondary loop to Highland Park and Glen Rae Manor subdivisions. The plans call for approximately 4,800 lineal feet of 8-inch SDR-21 Class 200 PVC pipe to be installed from Matthes Lane to Timer Street along MO-7 Highway.
CURRENT STATUS:
8/12/24 - Plans have been approved by the Missouri Department of Natural Resources (DNR) and are in preliminary review with the Missouri Department of Transportation (MoDOT).